CLIFF 297313 Ministry of BRITISH Transportation COLUMBIA © and Infrastructure BRIEFING NOTE FOR INFORMATION DATE: December 11, 2020 PREPARED FOR: Honourable Minister Rob Fleming ISSUE: Highway 1 Widening to the Fraser Valley SUMMARY: e Highway 1 widening to the Fraser Valley (Abbotsford) addresses mobility and reliability challenges for moving people and goods. e The segment between 216th and 264th Street was announced in 2019 and is currently in design with construction expected to get underway in late 2021. e The Fraser Valley Integrated Transportation and Development Strategy (ITDS) is in progress. It will look at traffic congestion and travel demand as well as examine and evaluate options for new transit and transportation initiatives in the Fraser Valley. e High-level planning is underway for widening between 264th Street to Whatcom Road. BACKGROUND: Highway 1 is a critical transportation link for the movement of goods and people. Traffic continues to increase on an annual basis, growing 11% over the last 5 years between 264" and Whatcom Road. Traffic volumes generally increase from east to west across the Highway 1 corridor between the Whatcom and the 264th Interchanges, with volumes greater than 80,000 vehicles per day between 264" Street in Langley to McCallum Road in Abbotsford, and then reducing to approximately 50,000 vehicles per day at Whatcom Road. Within the subject area of Highway 1 (264th to Whatcom), collision frequencies and severity are more than 10% higher than provincial averages across several sections and in both directions. Both the high collision rates and severities further contribute toward poor mobility and reliability of the Highway 1 corridor during weekdays and weekends. Highway 1 can also experience varied levels of mobility and reliability during weekday and weekend periods. In fact, peak vehicles speeds can be well below posted speeds (particularly in the eastbound directions) ranging anywhere from 20 to 60km/hr through much of Abbotsford. The variability of speeds in turn contribute toward higher collision rates and severities. Highway 1 widening is designed to ease congestion for growing areas of the Lower Mainland and reduce the frequency and severity of crashes along this provincially important corridor. The recently completed 4 km widening project for High Occupancy Vehicle (HOV) lanes between 202” and 216" Street as well as the completion of the new 216" Street Interchange have helped relieve congestion and improve operations. Design is underway for the continuation of 10 km of HOV lanes from 216" Street to 264" Street, a project that was announced in April 2019. Construction is expected to get underway in late 2021. PAST INTERACTIONS: None. Page 1 of Page Rav)21-10260 CLIFF 297313 Ministry of BRITISH Transportation COLUMBIA © and Infrastructure DISCUSSION: The existing HOV lanes, west of 216" Street, carry approximately 17% of the total daily traffic, meaning these lanes operate with less congestion than the general-purpose lanes, providing an incentive to carpoolers and transit riders. 8.13 The Fraser Valley Integrated Transportation and Development Strategy (ITDS) is underway and will look at traffic congestion and travel demand in the region, providing further insight into travel patterns on the Highway 1 corridor. It will examine and evaluate options for new transit and transportation initiatives in the Fraser Valley. The strategy is expected to take 18 months and be completed in spring 2022. The decision to widening Highway 1 over 22 km between 264" through to the Whatcom Interchange 8.13 While ITDS is being completed, planning for widening on the Highway 1 corridor between the 264th and Whatcom Interchange is in early stages of concept development. A variety of phasing, sequencing and procurements approaches for Highway 1 widening and associated interchange improvements are being evaluated as part of the review. Figure 1 outlines the recently completed Highway 1 Widening and 216" Interchange project between 202 to 216" Street, as well as the recently announced project between 216" and 264" Street, as the remaining segment between 264" and Whatcom Road. High level planning estimates are also under development to understand the order-of-magnitude costs associated with delivering the Highway 1 widening and interchange replacements. s-13; s.17 $8.13; S.17 The ministry intends to host a procurement workshop, in partnership with TI Corp, in early 2021 to better understand delivery options and timelines. FINANCIAL IMPLICATIONS: $8.13; S.17 PREPARED BY: REVIEWED BY: INITIALS. Janelle Staite, P.Eng Kevin Richter, Associate Deputy Minister Deputy Director, SCR Transportation & Infrastructure KR (250) 713-8763 Nancy Bain, EFO Finance and Management Services Department NB Page 2 ofPagg@ Raf 3021-10260 BRITISH COLUMBIA Copyright Ministry of Transportation and Infrastructure CLIFF 297313 Figure 1 - Overview Map of Highway 1 Widening to Fraser Valley Page Page BoffRA-2021-10260 (264 to Whatcom Interchanges) Project Improvement Highlights Copyright 2020-12-14 FOR DISCUSSION ONLY (CONFIDENTIAL 1 Page 4 of 23 TRA-2021-10260 APPROVED HOV Lane Widening (216* to 264") Features: Highway 1 (232 to 264") Copyright ONGOING: ~ (264t"to Mt Lehman) PROJECT STATUS: Problem Definition: q Existing Conditions q Future Base Conditions q Key Issues & Challenges Options Identification & Screening § Shortlist Options Development & Evaluation § Implementation Priorities (March 2021 Completion) Page 6 of 23 TRA-2021-10260 ONGOING: _ (264thto Mt Lehman) Preliminary Features: 232” to 264" Interchange 8.13; S.16 Page 7 of 23 TRA-2021-10260 ONGOING:* | (264t"to Mt Lehman) Preliminary Features: 264" Interchange & °° $8.13; $.16 Page 8 of 23 TRA-2021-10260 ONGOING: ~ (264thto Mt Lehman) Preliminary Features: 264" to Mt Lehman 8.13; S.16 Page 9 of 23 TRA-2021-10260 ANNOUNCED: Highway 1 Widening (264* to whatcom) Preliminary Features: Mt Lehman to Clearbrook 8.13; S.16 Page 10 of 23 TRA-2021-10260 ANNOUNCED: Highway 1 Widening (264* to whatcom) Preliminary Features: Clearbrook to McCallum $8.13; S.16 Page 11 of 23 TRA-2021-10260 ANNOUNCED: Highway 1 Widening (264* to whatcom) Preliminary Features: McCallum to Highway 11 Page 12 of 23 TRA-2021-10260 ANNOUNCED: Highway 1 Widening (264* to whatcom) Preliminary Features: Highway 11 Interchange 12-14 OR DISCUSSION ONLY (CONFIDENTIA 10 Page 13 of 23 TRA-2021-10260 ANNOUNCED: Highway 1 Widening (264* to whatcom) Preliminary Features: Highway 11 to Whatcom DENTIA 11 Page 14 of 23 TRA-2021-10260 ANNOUNCED: Highway 1 Widening (264* to whatcom) Preliminary Features: Whatcom Interchange Page 15 of 23 TRA-2021-10260 ANNOUNCED: Highway 1 Widening (264*to Whatcom) Potential Project Segments Copyright ON ONLY (CONFIDENTIAL 13 Page 16 of 23 TRA-2021-10260 Highway 1 Technical Planning, Design & Delivery Stages (DBB or DB) 2. Preliminary Design (10%) a. Design Criteria b. Lidar Mapping c. Preliminary Technical Investigations (i.e. geotechnical, environmental, archaeological, property, etc.) d. Concept Planning Refinements e. Concept Value Analysis f. 9g , Preliminary Design Drawings (Options) . Cost Estimates (30 to 50% including construction contingencies) and Risk Registry h. Stakeholder Engagement i, ProcurementScreen & Review j. Technical Reporting k. Stage 1 Business Case & Partnerships Ih rovals to Proceed Page 17 of 23 TRA-2021-10260 Highway 1” . Example DBB Integrated Project Delivery Schedule * Combined integrated corridor improvement plan (expand 264" to Mt Lehman). * Coordinated Preliminary & Functional Designs with Business Case Development & Approvals. + Advance Detailed Design, Tender & Construction incrementally from west to east. $.13;8.17 2020-12-14 FOR DISCUSSION ONLY (CONFIDENTIAL 15 Page 18 of 23 TRA-2021-10260 Highway 1” ; Example DB Advance Segment 1 & Combine 2-4 Delivery Schedule « Advance planning, design, business case, approvals and delivery (DB) for Segment 1. * Advance planning, design and approvals for Segments 2-4 and combine delivery (DB). 8.13; $.17 2020-12-14 FOR DISCUSSION ONLY (CONFIDENTIAL 16 Page 19 of 23 TRA-2021-10260 Highway 1 ~ Summary of Cost Estimates Highway 1 HOV/EV Lanes (264th Interchange to Whatcom Interchange) - Cost Estimate Summary 04-Dec-2020 | Version 2.0 sn Construction Value ($2020) Cost Adjustments ($2020) GRAND TOTAL Baseline Cost_| Contingency | __Subtotal Incirect Costs _| Total Excl Esc_| Escalation [interest During Construction 264th Street interchange Improvement $.13; 8.17 264th Street Park-and-Poo! Lot [Eastbound Truck Climbing Lane l232nd to 264th Bradner Overpass Structure Replacements [Eastbound HOV / EV Lane 264th to Mt. Lehman Westbound HOV / EV Lane Mt, Lehman to 264th Westbound Climbing Lane Extension 12 km west of Mt. Lehman to 264th SUBTOTAL - SEGMENT 1 Peardonuille Overpass Replacement & Reconfiguration [Eastbound HOV / EV Lane Mt. Lehman to McCallum Westbound HOV / EV Lane McCallum to Mt. Lehman Westbound Truck Climbing Lane McCallum to Clearbrook SUBTOTAL - SEGMENT 2 Highway 11 Interchange Replacement & [Eastbound + Westbound HOV / EV Lanes SUBTOTAL - SEGMENT 3 Whatcom Interchange - Stage 1 - Split Diamond Whatcom Interchange - Stage 2 - Full Buildout Eastbound HOV / EV Lane Highway 11 to Whatcom Westbound HOV / EV Lane Whatcom to Highway 11 SUBTOTAL - SEGMENT 4 GRAND TOTAL ($M) 2020-12-14 FOR DISCUSSION ONLY (CONFIDENTIAL 17 Page 20 of 23 TRA-2021-10260 Highway 1 — (264 to Whatcom Interchanges) Project Improvement Highlights Copyright 20-12-14 OR DISCUSSION ONLY (CONFIDENTIAL 18 Page 21 of 23 TRA-2021-10260 Issue: Appendix C-1 CORPORATE ISSUE/OPPORTUNITY NOTE PLATFORM COMMITMENT e Widen the Fraser Highway to ease congestion. © Continued Expansion of the Highway 1 corridor from 264" Street to Whatcom Interchange Background: e The Highway 1 corridor continues to experience significant congestion impacting regional and inter- regional movements between Metro Vancouver and the Fraser Valley. © The Highway 1 corridor from 264" Street (Langley) to Whatcom Interchange (Abbotsford) is 25km of 4-lane divided arterial highway and the major east-west connector for the Lower Mainland. e The Highway 1 corridor has an average annual daily volume of 91K vehicle trips. The corridor through this section divides the municipalities of Township of Langley and the City of Abbotsford. ¢ The Highway 1 corridor through this section has the following major interchanges: o Township of Langley = Hwy 264" Street 0°. City of Abbotsford = Mt. Lehman Road = Clearbrook Road = Peardonville Road = McCallum Road = Highway 11/1 Interchange = Whatcom Road Major development has already occurred near the corridor through the City of Abbotsford placing pressure on the existing interchanges. oS17 Issue/Opportunity: TransLink/BC Transit are looking to expand transit services between the Fraser Valley and Metro Vancouver. The Highway 1 corridor forms a primary connector for major transit nodes such as employment, education, and shopping. Five of the seven interchanges on the Highway 1 corridor from 264" to Whatcom Road would need be significantly reconfigured to accommodate future growth along the corridor. Improvements would need to consider transit services (stops, park & rides) as part of any design; and future economic development and growth adjacent to the corridor. Infrastructure projects on Highway 1 have been cost-shared between the Federal Government and the Local Municipalities. The ministry will need to seek funding partnerships from the Township of Langley and the City of Abbotsford to support this infrastructure. The Ministry of Municipal Affairs and Housing has stated that local Development Cost Charges (DCC) cannot be used by municipalities to fund non-municipal infrastructure. The Township of Langley and the City of Abbotsford have already raised this as a concern at UBCM and stated restricting the use of DCC’s will significantly decrease the opportunity for local municipalities to participate even though developments would benefit directly from an increased highway expansion. Page 22 of 23 TRA-2021-10260 e Future expansion of Highway 1 would need to be phased to prevent mobility issues in the Lower Mainland. The only alternative route to Highway 1 is Highway 7 which represents a significant detour for regional and inter-regional traffic. e The Ministry is completing a planning study to identify phasing options, issue identification, and planning level project estimates. This work will be completed by the end of November 2020. The Ministry would need to engage with 12 First Nations bands on future planning for this Highway 1 corridor. There has no engagement to date. . Page 23 of 23 TRA-2021-10260