Highway 10 overnight lane cuts from Dec 2, and no access from midnight to 4 am on Dec 8 to 11

The SkyTrain's Langley Launcher is crossing Highway 10 between Fraser Highway and 200 Street. Here are the exact nights, the hours with no access at all, and the detours the project lists.

If you drive Highway 10 between Fraser Highway and 200 Street after dark, the next two weeks are the ones to plan around. The Surrey Langley SkyTrain project posted a traffic notice on Nov 25: a giant yellow gantry called the Langley Launcher is building the guideway across the road, and the road has to give way for it.

Where
Highway 10 between Fraser Highway and 200 Street
Overnight work
Sat Nov 28, 10 pm to Fri Dec 11, 7 am (regular hours are Mon to Sat, 7 am to 10 pm)
One lane each way
Wed Dec 2 to Tue Dec 8, 9 pm to 5 am
No access
Tue Dec 8 to Fri Dec 11, 12 am to 4 am
Official detours
196 Street / Willowbrook Drive and 200 Street
Questions
1-844-815-6111 (24/7) or [email protected]

The two stages

Stage one, Dec 2 to Dec 8. Highway 10 is cut to a single lane in each direction between Fraser Highway and 200 Street, from 9 pm to 5 am. Expect slow going rather than a shutdown.

Stage two, Dec 8 to Dec 11. The lane cut runs 9 pm to 11:59 pm. Then, from 12 am to 4 am, there is no access to that stretch of Highway 10 at all. One lane each way returns from 4 am to 5 am. The project’s notice lists Tuesday, Dec 8 as both the last day of stage one and the first of stage two, so check its page that day for which one applies.

Cyclists and pedestrians are told to follow signs and the traffic control people on site.

Getting around it

The project’s own notice names two alternate routes: 196 Street / Willowbrook Drive and 200 Street. It doesn’t publish a turn-by-turn detour, so if you drive this stretch at night for work, try your alternate once in daylight before the closure starts. Buses are a separate matter: the notice sends riders to TransLink.ca for the latest on service in the area. Everything is marked “timelines subject to change”, and weather or a delay in the lift can move a night.

For current road closures in general, our guide to how to check road closures in Langley lists the official sources.

What the Launcher is doing

A launching gantry is a machine more than 100 metres long and over 440 tonnes. It lifts precast concrete segments, each around 28 tonnes, into place between the support columns, glues them with epoxy, pulls steel cables through to lock the span together, then slides itself forward onto the span it just built. The Langley Launcher started at Hillcrest-184 Street Station and is working east toward Langley City Centre Station, the end of the line. It has the biggest job of the project’s four gantries, roughly 1,350 of the more than 4,400 segments.

By late September the Province said it had built about 3 km of guideway and was moving over Willowbrook Drive toward the Willowbrook station site, with the whole guideway about 65% complete and the line still aimed at a 2029 opening. For the larger picture, see the Surrey Langley SkyTrain, explained, and our rant about the cones that arrived first.

Dates and hours are from the project’s notice posted Nov 25, 2026. If the project changes them, its page is the one to trust.